According to the officials of the Macedonian power utility ELEM, hydropower plant Splije near Debar and hydropower plant Globocica near Struga, both situated in Crni Drim catchment area, produced over 565 million kWh of electricity until midDecember, while their annual production plan for 2016 was exceed in the first ten months of the year.

HPP Spilje produced 340 million kWh in the period 1 January – 15 December 2016, which is 29 % more than planned for that period and 24 % above the annual production plan. HPP Globocica produced about 225 million kWh during this period, which is 18 % more than planned for the entire 2016.

These results are achieved mainly due to favorable hydrology in Crni Drim and Radika catchment area and successfully implemented maintenance of equipment at these hydropower plants. Debar and Globocica accumulations currently have water reserve to produce additional 20 and 13 million kWh of electricity respectively. The average water inflow is about 40 cubic meters per second at Debar accumulation and 30 cubic meters per second at Globocica accumulation.

Last year these two hydropower plants produced a total of 542 million kWh of electricity, which is considered as one of the best production results.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Lower wind and costly gas lift SEE power prices 11/9, but Serbia decouples

Southeast European day-ahead electricity prices strengthened on Friday as weaker wind generation, firm gas costs and reduced imports tightened the regional balance, while Serbia decoupled sharply from neighbouring markets. Hungary’s HUPX baseload price rose €5.60/MWh to €208.98/MWh, almost matching Romania...

Romania’s Cernavoda nuclear restart delayed by low Danube levels

Romania is dealing with a prolonged nuclear outage at the Cernavoda plant, with persistently low Danube river levels delaying restart conditions. Both reactors have been offline since Aug. 13. Unit 1 had already stopped in July before unit 2...

Econergy launches 70 MW battery with Parau 1 solar in Romania

Renewable developer Econergy has placed a 70 MW/141 MWh battery into commercial operation alongside its Parau 1 solar plant in Romania. The project is positioned as a merchant solar-storage combination. The investment in the combined development reached around €85...