Coal fired power plant Matrai reopened its lignite coal mine. Matrai company spent 8MEUR for the preparation of the coal operation restart which stoped production in 2004.

The company constructed four coal supply bridges, transport systems 10km lenght as well as new electrical supply network in the mine. After the initial removal of surface layers the lignite coal production should start in 2018 confirmed company CEO Bernhardt Luschper.

Matrai Eromu plans the life cycle of the mine for next 50 years and output of several hundreds million tons of coal. Annual capacity of the mine is 9 mil tons on locations Matra and Buk in northern Hungary.

Company produces 15% of total Hungary electricity generation and last year achieved income of 327MEUR. The owners of the company are RWE-EnBW 74% and state company MVM 24%., transmits Serbia-energy.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary leads SEE power-price surge as lower wind tightens Monday market

Hungarian electricity prices for Monday delivery surged as weekday demand recovered and wind generation declined, creating a high-price zone across Central Europe and widening price spreads with the southern Balkans. The HUPX baseload power price rose by €88.80/MWh from Sunday...

HSE construction permit for 1.38-MW solar and 1.25-MW/5-MWh battery in Zagorje ob Savi

Slovenian power utility HSE has secured a construction permit for a solar and battery project at the former Kamnolom Zagorje municipal landfill in Zagorje ob Savi. The development is linked to plans for site redevelopment in 2027. Planned generation,...

OMV Petrom to add 20-MW/40-MWh battery at Ișalnița solar site

OMV Petrom plans to add a 20-MW/40-MWh battery to its Ișalnița solar project in Romania, converting the development into a hybrid renewable generation and storage facility. The battery addition is linked to the Ișalnița site in Dolj county. Battery...
Supported byVirtu Energy