Coal fired power plant Matrai reopened its lignite coal mine. Matrai company spent 8MEUR for the preparation of the coal operation restart which stoped production in 2004.

The company constructed four coal supply bridges, transport systems 10km lenght as well as new electrical supply network in the mine. After the initial removal of surface layers the lignite coal production should start in 2018 confirmed company CEO Bernhardt Luschper.

Matrai Eromu plans the life cycle of the mine for next 50 years and output of several hundreds million tons of coal. Annual capacity of the mine is 9 mil tons on locations Matra and Buk in northern Hungary.

Company produces 15% of total Hungary electricity generation and last year achieved income of 327MEUR. The owners of the company are RWE-EnBW 74% and state company MVM 24%., transmits Serbia-energy.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia, Montenegro power prices climb as Hungary-Germany spread narrows

Electricity prices in Serbia and Montenegro rose sharply for Tuesday delivery, moving against declines in Hungary and Romania as southeastern Europe’s reliance on imports increased despite stronger solar generation. The divergence highlights tighter local supply conditions in parts of...

Slovenia restarts Sostanj unit 5 to meet district heating demand

Slovenia’s Sostanj thermal power plant has temporarily restarted unit 5 as colder weather increases district heating demand. Unit 6 remains under maintenance while unit 5 is brought back into service. Heat demand has reached approximately 400 MWh a day. Unit...

E.ON Hungaria €625 million grid programme targets 2,323 MW connection capacity

E.ON is planning a €625 million expansion of its Hungarian grid. Separately, E.ON Hungaria is outlining a €625 million network investment programme aimed at adding 2,323 MW of connection capacity by 2030. The plan is intended to support additional...