Hungary: MVM launches construction of 540 MW gas-fired power plant in Matra region

Hungary’s state-owned energy group MVM has begun construction of a new combined-cycle gas turbine (CCGT) power plant in the Matra region. Designed to produce 540 MW, the facility is scheduled for completion in 2028 and will play a significant role in ensuring the country’s electricity supply.

The project follows a procurement process launched in 2023 to build a modern gas-fired unit of up to 650 MW at the Visonta site, home to the existing coal-fired Matra power plant. In 2025, the contract was awarded to a consortium comprising Elsewedy Electric, West Hungaria Bau, and Status KPRIA. Once operational, the plant is expected to generate between 2 and 2.5 TWh of electricity annually, with a projected operational lifespan of at least 25 years.

The design features advanced technology, integrating a gas turbine prepared for green hydrogen use, a steam turbine, and a heat recovery boiler in a single system. This setup will provide greater operational flexibility, enabling the stable and adjustable power production needed to complement renewable energy sources in the national grid.

The Matra project is part of MVM’s wider strategy to expand Hungary’s gas-fired generation capacity. Alongside it, the company is developing two additional units of up to 500 MW each at the Tisza power plant site, to be built by a consortium led by Italy’s Ansaldo Energia and Turkey’s Calik Holding. Combined, the three facilities will add around 1,600 MW of new gas-based capacity to Hungary’s energy system.

Through these investments, MVM aims to better balance the increasing share of weather-dependent renewables while bolstering the country’s long-term energy security and grid stability.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Azerbaijan to raise gas deliveries for Niš 350 MW power and 150 MW heat project

Azerbaijan plans to increase gas deliveries to Serbia as the two countries advance a proposed 350 MW power plant and 150 MW heat plant in Niš. Azerbaijani officials said higher volumes would accompany development of the project. The Niš...

Paks nuclear output cuts linked to low wholesale prices amid Hungary’s solar growth

Hungary’s Paks nuclear plant has reduced generation again after electricity could not be sold economically during low-price hours. The latest curtailment reflects how rising solar output is affecting the country’s baseload market profile. Paks curtailment during low-price hours Paks cut...

Hungary granted temporary EU delay on Serbia gas capacity bundling rules

Hungary has received temporary approval from the European Commission to postpone full implementation of EU gas-capacity rules at its border with Serbia until the 2027/2028 gas year. The derogation relates to requirements that cross-border pipeline capacity be offered as...
Supported byVirtu Energy