Greece, DEDDIE to bolster distribution network in order to accommodate new RES capacity

Greek electricity distribution system operator DEDDIE, a subsidiary of Public Power Corporation (PPC), plans to use Recovery and Resilience Facility funding to cover investments for increasing capacity at certain existing low and medium- voltage substations in order to facilitate the entry of new RES units.

It is estimated that the capacity increase at these substations will enable connections to the distribution network for new RES units with a total capacity of 1,755 MW. This represents about 40 % of the total of 4,640 MW of new RES units envisaged by the National Energy and Climate Plan.

DEDDIE plans to invest some 30 million euros in these projects, of which 12 million euros will be provided via EU funding. All projects should be completed by the end of 2025.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy