Greece: Crete-Attica electricity interconnection enters final testing phase

Greece’s electricity transmission system operator, ADMIE, along with its project implementation arm Ariadne Interconnection, has reached a key milestone in the Crete-Attica electricity interconnection project. A final inspection at the Damasta converter station in Heraklion marks the beginning of the last phase of testing, ahead of the launch of the trial operation. The facility is expected to be energized next week, introducing reactive power into Crete’s electricity grid.

In parallel, trial electrification of the 400 kV cable system in Attica is underway. This segment connects the Koumoundouros converter station to the national grid, with full system testing scheduled to begin later in May.

By the end of the month, active electricity transmission from Attica to Crete is expected to begin. The Crete-Attica interconnection is Greece’s most ambitious and technically complex electricity transmission project to date.

Since early 2025, extensive testing has been carried out on all equipment. The 150 kV Damasta substation has been fully integrated into Crete’s network, and the 500 kV underground and subsea cables linking the two converter stations have passed all required tests. A significant step forward also came with the recent approval of the environmental permit for the new 150 kV Chania–Damasta transmission line in western Crete. This line will play a critical role in enabling the island’s dual interconnections—with both Attica and the Peloponnese—to operate smoothly and simultaneously.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy