Gross electricity production in the Federation of Bosnia and Herzegovina (FBiH) reached 461 GWh in May 2026. That level was 10% lower than in May last year, when output totaled 512 GWh. The generation mix showed hydropower at 30.6%, thermal power at 53.8%, and wind farms contributing 15.6% of gross production.

Generation mix and net output

Net electricity production in the FBiH stood at 411 GWh in May 2026. Hydropower accounted for 121 GWh, thermal plants produced 219 GWh, and wind farms generated 71 GWh. The figures reflect the split between gross generation shares and net output volumes.

Electricity trade flows

Imports fell to 89 GWh in May 2026, compared with 142 GWh in the same month of the previous year. Exports also declined to 56 GWh, versus 117 GWh recorded in May 2025. These changes were reported alongside the lower gross generation total.

Fuel production and coke shutdown

Brow n coal production increased to 311,688 tons, representing a 4.9% year-on-year rise. Lignite output dropped to 100,369 tons, down 23.6% from 131,316 tons in May 2025. Coke production fell to zero in May 2026 following the permanent closure of the Lukavac coke plant .

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

HEV earns more than EUR 2.5 million as Drina loss widens

HEV reported a profit for the first nine months of 2026, while Hidroelektrane na Drini’s consolidated loss widened. The results put cost control, hydrological conditions and asset performance in focus across the Republic of Srpska hydropower fleet.

Bosnia’s €1.5 billion gas link faces route and financing hurdles

Bosnia and Herzegovina’s Southern Interconnection is held up by disputed state property and disagreements over project implementation. While a former BH-Gas director says completion before 2030 looks unlikely, EU-backed efficiency financing is moving through a local bank.

ERS selects Hrgud consortium on nearly 82 million euros offer

Bosnia and Herzegovina’s ERS selected an El Promet-led consortium to build and finance the Hrgud wind farm under a fully financed 81.9 million euros offer. The utility chose it despite a rival construction bid that was 300,000 euros lower.