Supported byClarion Energy
HomeHydroERS Terminates Contract...

ERS Terminates Contract for Mrsovo Hydropower Plant Amid Redesign and Delay Challenges

The construction of the Mrsovo hydropower plant in Bosnia and Herzegovina has encountered significant setbacks, prompting state-owned utility ERS to terminate its agreement with Turkish contractor NGA. This decision comes as the project faces ongoing redesign disputes and delays that have hindered its progress since its inception.

ERS Director Luka Petrović indicated that unresolved technical and contractual issues rendered it impractical to continue under the current agreement. The project has already seen substantial financial commitments, including a 20 million euro advance payment to NGA and an additional 35 million euros allocated for acquiring the concession from Comsar Energy.

The core of the dispute revolves around required modifications to critical infrastructure components. Initially designed based on a 500-year flood level standard, regulators later mandated adherence to a more stringent 1,000-year flood scenario. This regulatory shift necessitated extensive design revisions affecting essential structures like the dam and river diversion system, which in turn escalated costs and altered technical specifications. The contractor’s refusal to accept these additional requirements led to a breakdown in negotiations.

Preparatory work had commenced on-site, including studies for a diversion tunnel intended to redirect the Lim River during construction. However, progress has stalled due to the lack of updated documentation that meets regulatory standards, preventing advancement to the permitting phase necessary for construction. Consequently, without securing a construction permit, further development was halted.

<pIn light of these challenges, ERS determined that amending the existing contract would introduce further financial uncertainty and potential delays. Therefore, the utility opted to terminate its relationship with NGA and initiate legal proceedings against the contractor while affirming that the hydropower project remains active.

Despite these ongoing obstacles, officials are optimistic about completing the hydropower plant. The project, initially launched in 2014 and relaunched in 2023 after state control of the concession was established, has yet to move beyond early development stages. This situation exemplifies broader issues related to delayed infrastructure projects linked to prior agreements with Comsar Energy.

The financial implications associated with the required design changes remain unclear as new technical proposals have not yet been submitted. Upcoming bidding procedures later this year are expected to clarify both the financial scope and timeline for completing the 36.8 MW Mrsovo hydropower facility.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia and Herzegovina drafts KfW loan for 132 MW Poklečani wind farm

KfW financing draft for Poklečani wind farm Bosnia and Herzegovina has approved a draft financing agreement with German development bank KfW for the 132 MW Poklečani wind farm. The project is described as one of the largest planned renewable-energy investments...

FBiH tenders 1.67 million litres of strategic diesel for Blažuj terminal

Procurement details for strategic diesel stocks The Federation of Bosnia and Herzegovina has launched a procurement for 1.67 million litres of diesel to expand strategic fuel stocks at the Blažuj petroleum terminal near Sarajevo. The contract is valued at approximately...

Bosnia advances €103 million financing for Poklečani wind and Elektrokrajina grid upgrades

Bosnia and Herzegovina has advanced around €103 million of proposed financing covering new wind capacity and distribution-grid upgrades. The package targets both additional generation and constraints in the network that increasingly limit renewable deployment. The Council of Ministers has...
Supported byVirtu Energy