Electrica signs EPC deal for Bihor 1 solar plus 18 MWh storage in Romania

Romanian electricity distributor and supplier Electrica has signed an engineering, procurement and construction (EPC) contract for the Bihor 1 renewable energy project. The development combines a large-scale solar power plant with battery energy storage. The agreement advances work on the facility’s main infrastructure and associated components.

EPC award via tender run by Electrica unit

The EPC contract was awarded following a competitive tender process conducted by Foton Power Energy, a wholly owned subsidiary of Electrica. The selected contractor has not been publicly disclosed. The contract scope includes delivery of the project’s main infrastructure and related facilities. The parties’ arrangements also cover the project’s subsequent operational support period.

Project footprint, capacities and grid connection works

The Bihor 1 site is planned for the municipalities of Cefa and Madaras in Bihor County. The solar component is set at an installed capacity of 78.8 MW. Battery energy storage will have a capacity of 18 MWh. As part of the works, the contractor will build a dedicated 110 kV substation to connect the plant to Romania’s national electricity grid.

EPC value and three-year operations and maintenance

The EPC contract is valued at approximately 36.6 million euros, excluding VAT. In addition to construction, the agreement includes operation and maintenance services for a period of three years after commissioning. The services are intended to support performance during the initial operating phase.

Status update and planned green bond financing

Bihor 1 entered Electrica’s renewable energy portfolio in September 2024. At that time, the utility acquired Foton Power Energy, the company responsible for developing the project. Electrica expects the investment to be financed primarily through funds raised from its green bond issuance completed in 2025.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Enexus to add 50 MWh battery storage to Romanian solar in Titu

Romanian renewable developer Enexus plans to install 50 MWh of battery storage alongside two solar projects in Titu, Dâmbovița county. The move extends Enexus’s cooperation with LONGi beyond photovoltaic modules. The hybrid configuration will pair solar generation with storage...

PPC moves 60 MW/129 MWh battery toward construction alongside Târgușor wind farm

PPC Renewables is advancing a 60 MW/129 MWh battery project positioned alongside its operating 120 MW Târgușor wind farm, bringing the asset closer to construction. The battery would be colocated with the wind facility in Constanța. The move is...

Romanian forward power clears above €205/MWh as winter risk prices in

Romanian electricity for January 2027 has traded above €205/MWh, indicating that the country’s scarcity premium is being embedded months ahead into winter procurement. The move follows recent trading activity in the forward market rather than being limited to volatile...
Supported byVirtu Energy