Wind farm Vratarusa 2 is planned to be built near the town of Senj. The High Administrative Court annulled the decision of the Croatian Ministry of Environmental Protection and Energy which said that it is not necessary to conduct an environmental impact assessment study for the 24 MW wind farm Vratarusa 2.

This decision marks the end of three years long lawsuit filed by the environmental organization BIOM against the Ministry of Environmental Protection and Energy. The suit was first filed at the Administrative Court in Rijeka, which rejected it. BIOM then appealed to the High Administrative Court pointing out that the vicinity of the proposed construction site is a known nesting area for endangered species of vultures and eagles.

The High Administrative Court upheld BIOM’s argument that the cumulative impacts of the Vratarusa 2 wind farm with the neighboring Senj wind farm, located two kilometers away, had not been assessed. According to the conclusion of the High Administrative Court, the first instance court failed to correct the stated shortcoming, which BIOM pointed out in the lawsuit. Also, the High Administrative Court found that the Ministry’s allegations that the cumulative impacts had been assessed were not true.

 

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Italy and Croatia see higher LNG inflows as Greek receipts decline

LNG inflows increased in Italy and Croatia during the week to 20 September, adding to imported gas availability as European markets prepared for the upcoming winter withdrawal season. Italy recorded 4,373.49 GWh of LNG inflows, an increase of 23.37% from...

Croatia’s renewable output plunges as hydro gains fail to offset rising power imports

Croatia recorded a 54.3% decline in variable renewable generation in the week to 20 September, marking one of the steepest drops in the region, while the country increased its reliance on net electricity imports. Hydropower generation provided a partial offset,...

European Energy brings 27 MW Tsoukes Sarres wind farm online in Greece