Croatia: RP Global begins construction of largest solar power plant with EBRD backing

In late April, Austrian renewable energy company RP Global began construction of the 21 MW Novalja solar power plant on the Croatian island of Pag. This project is set to become the largest solar facility in Croatia to date.

The European Bank for Reconstruction and Development (EBRD) is supporting the development with a senior, non-recourse loan of up to 12.2 million euros. This financing is provided under the EBRD’s InvestEU Framework for Sustainable Transition.

The EBRD’s contribution is divided into two parts: an initial tranche of 7.2 million euros and a second tranche of 5 million euros, which includes a 20 percent first-loss risk coverage. The total estimated investment in the project is 16.3 million euros.

What sets the Novalja plant apart is its hybrid revenue model. While the project will benefit from Croatia’s national renewable energy support schemes in its early stages, it is designed to gradually transition to merchant market sales over time. This flexible offtake approach represents an innovative step in project financing. In 2023, Croatia’s energy market operator HROTE awarded support to 420 MW of solar and hydropower capacity, including 15 MW from the Novalja project.

The solar plant will include 35,776 panels and is expected to generate approximately 31,000 megawatt-hours of electricity annually—enough to meet the needs of about 12,000 households.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Croatia launches €38 million household clean-energy grants with battery storage

Croatia opened applications on Tuesday for a €38 million household clean-energy programme that includes support for battery storage for the first time. Authorities said the measure is intended to shift more rooftop solar output into evening demand periods. The...

Croatia records highest summer hourly demand as evening peak surpasses winter

Croatia’s electricity demand reached a record summer hourly level of 3,400.5 MWh in August, exceeding both the country’s previous summer maximum and the latest winter peak. The highest point occurred at around 21:00, after most photovoltaic output had disappeared...

Croatia records new August summer demand peak at 21:00

August peak exceeds prior summer and latest winter maximum Croatia registered a new record summer electricity demand peak in August, with the highest load occurring in the evening hours. Hourly consumption reached 3,400.5 MWh at 21:00, surpassing the previous summer...
Supported byVirtu Energy