Croatia: Power utility HEP to invest 218MEUR in NPP Krsko extension of operating span until 2043

NPP Krško will not stop its operation in 2023 because its operating life is extended until 2043, meaning that Croatian power system will have another 28 years of electricity from this fundamental, stable and reliable source.

Based on the results of the study on economic justification of extension of Nuclear Power Plant operating life, created by PricewaterhouseCoopers from London, the members of the Supervisory Board of NPP Krško agreed on late November 2014 to extend its operating life until 2043. Regular operating lifetime of NPP Krško was supposed to end in 2023. PWC’s study confirmed that the lifetime extension of NPP Krško is better option than investing in replacement capacities, regardless of whether they are hydro, thermal or nuclear sources, as well it is cheaper than purchasing electricity in the market.

All that preceded the drafting of foregoing study and the decision of Supervisory Board of NPP Krško was revealed by its President Kazimir Vrankic HEP’s Journal’s new edition. He stressed that since the opening of NPP Krško, HEP has been continuously investing in technological renovation and maintenance of the plant, so that Krško today achieves a very high level of security, operational stability and reliability. It performed best in EU’s so-called stress test examinations, and according to the indicators of safety and reliability it belongs to the world top.

However, the Slovenian Nuclear Safety Administration (SNSA) ordered the implementation of additional nuclear safety projects in NPP Krško, after the accident at the NPP Fukushima. The management set these projects as a key prerequisite for the approval of plant operation after 2023. Thus, the nuclear security upgrade program was prepared in NPP Krško, and later accepted by the SNSA. The Supervisory Board of NPP Krško then approved the long-term investment plan, with eight nuclear safety projects worth 218 million euros. Given the size of investments, HEP and GEN Energy as co-owners of the plant, agreed in early November 2013 on the preparation of the study on economic justification of extension of Nuclear Power Plant operating life, was stated by HEP.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungarian power prices surge as weak wind drives Southeast Europe higher

Hungarian electricity prices jumped nearly 12% for Tuesday delivery, driving a broader increase across Southeast Europe as a sharp decline in forecast wind generation and higher electricity demand increased the region’s reliance on imports, while German power prices moved...

TDI financing for 58 MW Iratoșu solar plant in western Romania

TDI Renewables has secured €25.5 million in financing from Raiffeisen Bank International for its 58 MW Iratoșu solar power plant in western Romania. The project is located in Arad county and is part of a broader development programme that...

Nuclearelectrica revises 2026 outlook as Cernavoda outages drive replacement power costs

Romanian nuclear producer Nuclearelectrica has reduced its forecast for 2026 net profit by 42.9% to €221 million. The company attributed the change to prolonged outages at Cernavoda, which have lowered electricity sales and required purchases of replacement power. Revised...
Supported byVirtu Energy