Bulgarian coal-fired thermal power plant (TPP) Maritsa East 2 received a licence to operate its Unit 7 following an overhaul.

The licence was granted on January 6 after the unit passed a 72-hour operational test, the TPP operator said in a notice published on its website.

As a result of the upgrade, the plant’s efficiency was raised and the life-span of its equipment was extended by 20 years, the company added. The plant’s capacity too was increased, it said, without quoting figures.

Maritsa East 2, a subsidiary of the state-run Bulgarian Energy Holding, has an installed capacity of 1,600 megawatts.

The unit’s rehabilitation was part of a project for the introduction of uniform steam turbines in the plant’s units 5, 6, 7 and 8 with the aim to cutting production costs for maintenance, repairs and spare parts. The value of the project was not disclosed.

Unit 5 has already been upgraded and put in operation in December last year.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia drives Southeast European power price decline as renewables narrow regional spreads

Southeast European day-ahead electricity prices fell sharply for Wednesday delivery, as stronger wind and solar generation, improved domestic output and lower import requirements eased the supply pressure that had pushed regional markets well above Western European benchmarks a day...

Bulgaria launches 300 MWh Tesla battery project as energy storage expansion gains momentum

Bulgaria has begun construction of a 300 MWh battery energy-storage facility in Tvarditsa, marking the first stage of a broader investment programme worth more than €350 million. The programme includes three battery projects with a combined storage capacity of...

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...
Supported byVirtu Energy