Unit 6 at Bulgaria’s Kozloduy Nuclear Power Plant is back online following its annual maintenance, reconnecting to the national electricity grid on the evening of 1 December.

The maintenance program, which started on 25 October 2025, included thorough preventive inspections, servicing of critical systems, and all tasks required under the plant’s annual upkeep schedule. During this overhaul, the unit also received a new load of nuclear fuel for its 31st operating cycle. Plant engineers highlighted that these measures are designed to enhance operational safety and support the facility’s long-term performance.

In line with operational procedures, Unit 6 is gradually increasing output through a step-by-step power ramp. Meanwhile, Unit 5 continues to operate according to Bulgaria’s electricity production plan.

Earlier in the year, Unit 6 underwent a short-term outage to repair a coolant leak in the third steam generator. The precautionary shutdown was implemented to maintain strict safety standards and ensure reliable electricity generation.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bulgaria electricity output up 15.6% in July as demand falls

Bulgaria’s electricity production rose 15.6% year on year to 3,779 GWh in July, while domestic consumption declined 4.1% to 2,652 GWh. The gap between output and demand widened over the month. Compared with June, generation increased 19.5%, while consumption...

Bulgargaz obtains 10-year wholesale gas licence for Serbia

Bulgargaz, the Bulgarian state-owned gas supplier, has secured a 10-year wholesale gas licence in Serbia. The permit authorises the company to conduct commercial gas trading on the Serbian market. The development extends Bulgargaz’s trading footprint across Southeastern and Central...

Kozloduy unit 5 output cut as Danube levels fall below cooling-water thresholds

Bulgaria’s Kozloduy nuclear power plant has reduced output from unit 5 after exceptionally low Danube levels constrained cooling-water availability. Regulators said the plant remains within safe operating limits. The reduction is linked to river conditions rather than an identified...