Bosnia and Herzegovina: Unit 7 at TPP Tuzla will probably not happen

Last month, General Electric withdrew from the project as the supplier of equipment and in order to continue with the project, the Chinese contractor Gezhouba Group requested an amendment to the signed contract, which is not possible without the consent of the Parliament. Thus, changing any detail of the contract would involve a renegotiation process and re-approval by the said institution.

According to Bosnian media, the deadline for amending the contract signed with the Chinese partners for the construction of unit 7 at coal-fired power plant Tuzla has passed. Power utility EPBiH is prepared to terminate the contract, but the final decision will be made by the FBiH Parliament.

Namely, in January 2021, Chinese partner has informed EPBiH that the boiler for the unit will be supplied by Shanghai Boiler Works Co. instead of General Electric. Three months later, EPBiH Supervisory Board adopted a conclusion, according to which, the company endorsed the original contract, without any changes regarding the supplier of the equipment.

EPBiH informed the Chinese partner that in order to protect its interests it will take all measures provided by law. The company has invested almost 10 million euros in preparatory works for the project and already paid 107 million euros as an advance, while the contractor has delayed the start of the construction on several occasions.

In November 2017, EPBiH signed a loan agreement with Chinese Exim Bank for financing the construction of unit 7 at TPP Tuzla on the sidelines of a meeting of the heads of Governments of China and 16 Central and East European countries held in Budapest. The net agreed price under the EPC contract is 722.35 million euros (without VAT). The maturity of the loan from China’s Exim Bank is 20 years, with a 5-years grace period. The loan will cover 85 % of the investment, while the remaining 15 % will be provided from EPBiH’s own funds. TPP Tuzla has 6 units with overall output of 715 MW. New unit 7 will be replacement capacity for units 1 and 2 (32 MW each), which have already been shut down and units 3 (100 MW) and 4 (200 MW) which should be put out of operation in 2018, but will most likely continue to operate until 2020. When unit 7 is completed, it will provide almost a quarter of electricity produced by EPBiH.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...

EPBiH coal shortages raise risk of further electricity tariff pressure in 2026-2027

EPBiH, the state-owned power utility in Bosnia and Herzegovina, faces renewed electricity-price pressure as coal supply problems contribute to losses. The company could see pressure for another electricity-price increase by late 2026 or early 2027, according to the conditions...

Republika Srpska to raise electricity prices from 2027 amid Ugljevik coal issues

Businesses in Republika Srpska are expected to see higher electricity prices starting in January 2027, with households facing increases from March. The authorities are also seeking to strengthen the power sector’s finances while addressing coal supply problems that could...
Supported byVirtu Energy