Hidroelektrane na Drini, a subsidiary of power utility ERS and the operator of the Višegrad hydropower plant, reported that the plant generated 89.21 GWh of electricity in January 2025. This marks a 21.9% increase compared to December 2024, when production stood at 73.18 GWh. However, output was significantly lower than in January 2024, when the plant generated 150.81 GWh.

In 2024, HPP Višegrad produced a total of 733 GWh of electricity, a sharp decline from the 1,224 GWh generated in 2023.

Commissioned in 1989, HPP Višegrad has an installed capacity of 315 MW (3 x 105 MW) and an average annual electricity generation of 1,010 GWh. The plant achieved its record annual production in 2010, reaching 1,283.05 GWh.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Putin talks prompt Republika Srpska to seek unchanged Russian gas pricing

Republika Srpska expects Russian gas pricing to remain unchanged, SNSD leader Milorad Dodik said after meetings with Russian President Vladimir Putin in Moscow. Dodik also said Republika Srpska expects Russian gas supplies to continue under existing pricing terms. The...

Business electricity prices up 7.7% for medium-sized commercial users in Bosnia

Electricity prices for medium-sized commercial consumers in Bosnia and Herzegovina rose 7.7% year on year in the first half of 2026. The increase exceeded the rise recorded for households over the same period. The data indicate higher electricity costs...

Solar Agroland wins 50-year concession for Bileća 1 solar and storage project

50-year concession in Republic of Srpska Solar Agroland has secured a 50-year concession for the Bileća 1 solar and battery storage project in Bosnia and Herzegovina’s Republic of Srpska. The company’s final layout is still subject to planning decisions and...
Supported byVirtu Energy