Bosnia and Herzegovina, FIPA visited the construction site of the Ivovik wind farm

Representatives of the Agency for the Promotion of Foreign Investments in Bosnia and Herzegovina (FIPA) visited the construction site of the Ivovik wind farm near Livno.

Director of the project company Xiao Xin said that the wind farm will consist of 20 turbines with power output of 4.2 MW each, totaling 84 MW, adding that the project will cost around 68 million euros.

So far, around 22 million euros has already been invested in the project. The project company has environmental, spatial and construction permits, as well as all permits related to the production of electricity, while the concession for a wind farm was issued for a period of 30 years. The installation of the first wind turbine has begun, while the foundations for the others are being laid.

In September, following Bosnia’s Herzeg-Bosnia Canton Government’s approval of the request of Sinohydro Holding, a subsidiary of Chinese Powerchina Resources, for the sale of its 51 % stake in local company which in charge of the construction and operation of wind farm Ivovik, the share was sold to Luxembourg based Ivovik Wind Power.

The shareholders in the project company VE Ivovik are now: Ivovik Wind Power with 51 %, CNTIC Capital, a Hong-Kong based subsidiary of China National Technical Import & Export Corporation, with 39 % stake and individual investor Ekrem Nanic with 10 % stake.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...
Supported byVirtu Energy