Supported byClarion Energy
HomeElectricityBosnia and Herzegovina:...

Bosnia and Herzegovina: EPBiH recovers €126.5 million advance after terminating Tuzla unit 7 construction contract

Bosnia’s state-owned power utility, EPBiH, has successfully recovered the full advance payment of 126.5 million euros from the Chinese contractor after terminating the contract for the construction of Unit 7 at the Tuzla coal-fired thermal power plant.

The unit 7 project, which has attracted significant public interest, faced delays and issues from the beginning. EPBiH management exercised caution in communicating the status of the project to avoid misinformation while ensuring effective negotiations and protecting the company’s interests. Now, the utility has decided to share the results of the negotiations.

The Engineering, Procurement, and Construction (EPC) contract for the 450 MW Unit 7 at Tuzla, valued at over 700 million euros, was signed in August 2014 with two Chinese contractors: China Gezhouba Group Company and China Energy Engineering Group Guangdong Electric Power Design Institute Co. In June 2020, EPBiH made an advance payment of 126.5 million euros to the contractor. However, in August 2020, the contractor informed EPBiH that it was unable to fulfill the contract due to issues in procuring key equipment from General Electric.

By January 2023, the contractor had still not met its contractual obligations or provided any alternative solutions. In response, the previous EPBiH management, with the approval of the FBiH Government, issued three warnings to the contractor, signaling the potential termination of the contract. The final warning was given in July 2023, setting a 90-day deadline for the contractor to fulfill its obligations.

After taking office in August 2023, the current management of EPBiH hired a renowned international legal team to protect the company’s interests. Despite the contractor’s continued failure to meet its obligations, EPBiH, with prior approval from the FBiH Government, officially terminated the contract in December 2023 and began negotiations for an amicable resolution of the outstanding issues.

Following months of negotiations, EPBiH successfully recovered the full 126.5 million euros advance payment, marking a resolution to the long-standing issue.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...

EPBiH coal shortages raise risk of further electricity tariff pressure in 2026-2027

EPBiH, the state-owned power utility in Bosnia and Herzegovina, faces renewed electricity-price pressure as coal supply problems contribute to losses. The company could see pressure for another electricity-price increase by late 2026 or early 2027, according to the conditions...

Republika Srpska to raise electricity prices from 2027 amid Ugljevik coal issues

Businesses in Republika Srpska are expected to see higher electricity prices starting in January 2027, with households facing increases from March. The authorities are also seeking to strengthen the power sector’s finances while addressing coal supply problems that could...
Supported byVirtu Energy