Bosnia and Herzegovina, Construction of Ivan Sedlo wind farm started

Suzlon Wind Energy BH, a local subsidiary of Danish Suzlon Energy, started the construction of 25 MW wind farm Ivan Sedlo in Hadzici municipality, a project worth 35.8 million euros.

The Government of the Sarajevo Canton said that the wind farm should be commissioned in 18 months. It will generate 70 GWh of electricity per year, which would cover around 6 % of the Canton’s electricity consumption. Suzlon Energy has an option to increase the wind farm’s capacity to 35 MW at the later date.

The start of the construction of the wind farm was initially planned for 2019. However, in early 2021, the Cantonal Government signed an annex to the agreement with Suzlon Wind Energy BH, which envisaged the reduction of wind turbines from twelve to five, keeping the original installed capacity of 25 MW.

In July, The Government of the Federation of Bosnia and Herzegovina (FBiH) has approved the issuance of energy permit to Suzlon Wind Energy BiH for the construction of Ivan Sedlo wind farm in Hadzici municipality. Ivan Sedlo wind farm will consist of five wind turbines, each with power output of 5 MW.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Business electricity prices up 7.7% for medium-sized commercial users in Bosnia

Electricity prices for medium-sized commercial consumers in Bosnia and Herzegovina rose 7.7% year on year in the first half of 2026. The increase exceeded the rise recorded for households over the same period. The data indicate higher electricity costs...

Solar Agroland wins 50-year concession for Bileća 1 solar and storage project

50-year concession in Republic of Srpska Solar Agroland has secured a 50-year concession for the Bileća 1 solar and battery storage project in Bosnia and Herzegovina’s Republic of Srpska. The company’s final layout is still subject to planning decisions and...

Federation of Bosnia electricity generation up 15.8% in August as trade falls

Electricity production in the Federation of Bosnia and Herzegovina increased in August compared with August 2025, while both imports and exports declined from year-earlier elevated levels. Gross production reached 529 GWh, rising 15.8% from 457 GWh in August 2025....
Supported byVirtu Energy