BiH: TPP Ugljevik has not started to deliver electricity to Slovenia

Not even two months after the adoption of the decision that RiTE Ugljevik should deliver balancing energy to Slovenian company HSE, the delivery of electricity has not started.

According to the ruling of the Belgrade arbitration court, TPP Ugljevik is obliged to deliver one-third of electricity generated by the plant to the Slovenian system. But, according to the plants union organization, its parent company, power utility ERS, directed the produced electricity to its own system and sold it on the international markets.

In July, an arbitration court ruled that RiTE Ugljevik has to pay 67 million euros in compensation to Slovenian electricity producer HSE. The court found that the Slovenian company is entitled to compensation for electricity not delivered by RiTE Ugljevik in the period from June 2011 to December 2021.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

HSE trial operation expands Prapretno solar complex with 7-MW battery storage

HSE begins trial operation at Prapretno 2 and 3 Slovenian state-owned utility HSE has started trial operation of the Prapretno 2 and Prapretno 3 solar plants. The start of commissioning expands the site into Slovenia’s largest operating photovoltaic complex. The...

ERS revises qualification rules for 60-MW Hrgud wind farm tender

Bosnian Serb power utility ERS has eased qualification requirements for the 60-MW Hrgud wind farm tender, following an appeal against the procurement documentation. The change widens the pool of potential bidders for the project’s €95 million engineering, procurement, construction...

HSE construction permit for 1.38-MW solar and 1.25-MW/5-MWh battery in Zagorje ob Savi

Slovenian power utility HSE has secured a construction permit for a solar and battery project at the former Kamnolom Zagorje municipal landfill in Zagorje ob Savi. The development is linked to plans for site redevelopment in 2027. Planned generation,...
Supported byVirtu Energy