250MEUR FGD project starts on TENT power plants, tender invitation by end of the 2012

Thermal Power Plants company Nikola Tesla is preparing for biggest environmental and investment project in 2012/2013. Flue gas desulphurization project in value of 250MEUR will be implemented on location TENT A power plant. TEPSCO is a consultant for preparation of tender documentations which will be publicly announced by end of 2012 and all interested referenced companies will have the opportunity to bid for this large project.

Representatives of the Japan International Cooperation Agency (JICA) and the Japanese consulting firm TEPSCO (Tokyo Electric Power Service Co.) discussed today in the Corporate Enterprise “Nikola Tesla” in Obrenovac with the management of PE EPS and TENT the beginning of the project on flu gas desulphurization at TENT-A. Choosing TEPSCO, Japanese consultant for preparation of tender documents, the realization of the highest environmental investment in the country practically started for which the Japanese government approved a loan of EUR 250 million, with very favorable repayment period.

Dragomir Markovic, General Manager of EPS, on this occasion once again thanked the Government of Japan for support of affordable credit as well as the JICA representatives for their assistance to conclude successfully these complex negotiations. He expressed hope that the ongoing activities of desulphurization project will be successfully implemented and will be a “starting point for the continuation and expansion of cooperation with the Japanese side of the field activities of EPS, especially the design and construction of new power plants, primarily, the unit B -3 at U

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

SEE electricity markets: Serbia leads regional prices as Hungarian-German spread widens and import dependence persists

Southeast European electricity markets remained under significant price pressure for delivery on 13 October, with Serbia recording the highest day-ahead price among the regional markets covered, while a widening premium between Hungary and Germany highlighted persistent constraints on electricity...

Romania reviews Doicești SMR after internal check leaves over 80% conditions unresolved

Romania’s nuclear power utility Nuclearelectrica is reassessing the future of the Doicești small modular reactor project following an internal review. The review concluded that more than 80% of the conditions linked to its February 2026 investment decision remained unresolved....

CGES approves €40 million grid deal for 488 MW Sinjajevina wind connections

High-voltage link for Sinjajevina 1 and Sinjajevina 2 Montenegro’s electricity transmission operator CGES has approved an arrangement covering approximately €40 million of high-voltage infrastructure to connect two wind farms with a combined capacity of 488 MW. The plan is aimed...
Supported byVirtu Energy