Zijin in Bor, Serbia invests in copper smelter reconstruction

Zijin Bor Copper plans to complete the reconstruction of the Bor copper smelter by the end of 2022 and will attach priority to the installation of a flue gas capturing and desulphurisation system, which will be completed by the end of 2021, it said. Zijin Bor Copper’s deputy managing director Simon Ling said in June that the company plans to invest $1.26 billion in capacity and equipment overhaul, as well as environmental and safety improvements at the Bor mining complex.

Zijin Bor Copper, the Serbian unit of China’s Zijin Mining Group, plans to invest a total of $265 million (225 billion euro) in the reconstruction of the Bor copper smelter, it said.

The company started the project in September, two months ahead of schedule, due to the increased flue gas emissions caused by a malfunction in the plant equipment, which negatively affected air quality in Bor, Zijin Bor Copper said in the latest edition of corporate newsletter Kolektiv.

So far, the company has invested a total of $38.15 million in environmental improvements and plans to make further $120 million investments in the field throughout the working life of the mine, it added.

According to media reports, the Bor city government has filed a criminal complaint against Zijin after measuring stations of the country’s Environmental Protection Agency registered excessive SO2 levels for three days in a row in September.

Source: seenews.com

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Djerdap 3 pumped-storage: Bechtel-Enka qualifies as Serbia prepares planning

Serbia has advanced work on the proposed Djerdap 3 pumped-storage hydropower project, with a Bechtel-Enka consortium qualifying for the next stage of government negotiations. At the same time, a Serbian engineering consortium is preparing the project’s planning framework. The...

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Serbian renewable projects face new contractual challenges on the Hungary export corridor

Export PPAs can expand market access for wind and solar projects, but the revenue ultimately reaching developers depends on delivery rights, trading costs and the share of output that qualifies for actual-emissions treatment. Serbian wind and solar developers targeting Hungarian...
Supported byVirtu Energy