Supported byClarion Energy
HomeNuclearSlovenia: The capacity...

Slovenia: The capacity of the Krsko NPP new unit could be expanded to 2.4 GW

Slovenian energy group Gen-Energija considers expanding the capacity of a planned second unit at the Krsko nuclear power plant to 2,400 MW from 1,100 MW, according to local media.

Gen-Energija decided to expand the range of possible options and to pave the way for more powerful units, in the extreme case in the range of up to 2400 MW, or, given that the chosen place in Vrbina pri Krsko allows, to even decide on two nuclear units, NPP Krsko CEO Dejan Paravan said to news agency STA.

In this scenario, France’s EDF and South Korea’s KHNP could participate in the project, as so far only Westinghouse has offered to provide a unit of 1,100 MW, Paravan added.

The planned capacity increase was made possible by a change in Slovenian legislation, which no longer sets the limit at 1,100 MW. The energy crisis led to an even greater need for electricity, and the interest of neighbouring countries in co-investing in the project also increased, he noted.

Earlier this year, energy minister Bojan Kumer said Slovenia will be able to make a decision on the construction of a second unit at Krsko NPP in 2024 at the earliest. The timing of the decision, which will likely be voted on at a referendum, depends on the conclusions of a feasibility study being prepared by Gen-Energija as a potential investor, Kumer said.

Krsko NPP, located in Slovenia near the border with Croatia, generates 40% of Slovenia’s electricity output. The NPP is located around 100 kilometres from Austria and operates a Westinghouse pressurised light water reactor with a 2,000 MW thermal power capacity. The operating company Nuklearna elektrarna Krsko (NEK) is co-owned by Gen-Energija and Croatian power utility Hrvatska Elektroprivreda (HEP), SeeNews reports.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

GEN posts near-€160m profit as Slovenia progresses Krsko nuclear planning

GEN, the Slovenian state-owned energy group, earned almost €160 million in 2025. The company reported that generation exceeded its plan during the year. GEN also continued major investment across its nuclear and renewable portfolio. GEN’s power plants produced 3,427.7 GWh...

Krško nuclear unit restores full output after Sava River restrictions eased

Slovenia’s Krško nuclear power plant has returned its reactor to 100 per cent power following cooler weather, rainfall and improving conditions on the Sava River. The changes eased environmental restrictions that had constrained production since early August. Derating steps...

Krško output derated to about 80% amid Sava heat and low-flow cooling limits

The 730 MW Krško nuclear power plant has cut generation after high temperatures on the Sava and low river flows limited available cooling capacity. The reduction extends the effect of summer hydrological stress into the Slovenian and Croatian electricity...
Supported byVirtu Energy