Slovenia, NPP Krsko received an environmental permit to extend its working life

The Slovenian Ministry of the Environment has announced that it has issued a permit to extend the life of the Krsko nuclear power plant (NEK) until 2043.

The procedure included an environmental impact assessment to examine potential improvements that would reduce the likelihood of environmental accidents, resistance to climate change and external factors, as well as the impact on water, regarding the trend of warming watercourses in Slovenia, said Environment Minister Uros Brezan in a statement issued on Monday.

Representatives of Slovenia’s neighbors – Croatia, Austria, Italy and Hungary, as well as Germany – took part in consultations related to the project, while delegations from Italy and Austria additionally visited the power plant, the government announced. In July 2021, the Ministry of Infrastructure issued an energy permit for the construction of a second reactor at the Krsko NPP, and that decision drew criticism from Austria, whose constitution prohibits the use of nuclear fission in energy supply.

As many as 50 experts participated in the environmental impact assessment, and the action plan should be completed by the middle of 2023, said the president of the Management Board of the Krško Nuclear Power Plant operator. He added that physical technological upgrading of the power plant will not be required.

NEK expects to complete the installation of the facility for dry storage of spent nuclear fuel by the middle of this year, which will fulfill all the conditions and implement the decisions of the competent authorities for the extension of the operation of the power plant.

In November, NEK completed the planned overhaul of the power plant, which included the replacement of a total of 56 out of 121 fuel elements and a standard program of maintenance and inspection of mechanical, electrical and instrumentation equipment. The nuclear power plant was originally designed to operate until 2023. However, in 2016, GEN energy and HEP decided to extend its life by 20 years, until 2043, on the condition that the plant passes a safety inspection every 10 years.

Sign up for updates & special reports

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Krško nuclear plant generates 487,438 MWh in September 2026, misses target

The Krško nuclear power plant, jointly owned by Slovenia and Croatia, produced 487,438 MWh of net electricity in September 2026. Output was 1.53% below the plant’s monthly production target for the month. The reported shortfall followed a plan to...

Enery begins Jezerce hybrid solar-battery build with €88/MWh municipal offtake

Vienna-based renewable energy group Enery has started construction of a hybrid solar and battery facility in Slovenia at the Jezerce project near Divača. The installation combines 7.68 MW of photovoltaic capacity with 12 MWh of electricity storage. Project location...

Slovenia’s industrial power-sharing model delivers measurable savings as market scales

Slovenia’s electricity-sharing market is beginning to deliver measurable savings for industrial consumers, strengthening the case for an emerging energy-service model focused on allocating existing renewable generation more efficiently rather than building additional generation assets. Slovenian energy technology company SunContract said...