Slovenia: NPP Krško back online after scheduled maintenance completion

Slovenia’s only nuclear power plant, Krško, was reconnected to the national electricity grid on Tuesday, 28 October, following the completion of its scheduled maintenance program. Over the next several days, the plant will gradually increase power output in line with strict safety procedures, the operator announced.

The month-long overhaul, which began on 28 September, included refueling operations, detailed maintenance, and extensive inspections of mechanical, electrical, and instrumentation systems. Modernization works were also carried out to further enhance safety, reliability, and overall performance.

Within the reactor core, 56 of the 121 fuel elements were replaced, securing a stable energy supply until the next maintenance cycle planned for spring 2027. The successful refueling ensures continuous operation and sufficient capacity for the next 18 months.

After completing hundreds of component and system tests, the Krško Nuclear Power Plant confirmed that all equipment meets operational and safety standards. For 2025, the plant expects to generate around 5.4 TWh of electricity, contributing significantly to the stability and energy security of both the Slovenian and Croatian power systems.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia appoints GEN leadership ahead of Krško 2 nuclear project decisions

New executives at GEN energija and GEN-I Slovenia has appointed new leadership at state-owned GEN energija and electricity supplier and trader GEN-I, changing management at two of the country’s key energy companies as decisions on the proposed Krško 2 nuclear...

Slovenian household electricity and gas prices rise in Q2 2026

Slovenian household electricity and natural gas prices increased in the second quarter of 2026. Households paid an average €0.215/kWh for electricity and €0.087/kWh for natural gas. The changes were measured against the first quarter. Quarterly changes for household tariffs Electricity prices...

Slovenia appoints new GEN energija and GEN-I leaders for Krško 2 and Mokrice

Slovenia has appointed new leadership at state energy group GEN energija and electricity trader GEN-I, following a change in the country’s government. Andrej Vizjak, incoming chief executive at GEN energija, said work on the planned Krško 2 nuclear project...
Supported byVirtu Energy