Serbia moves forward with Bistrica pumped-storage hydropower project

State-owned utility EPS has initiated a public procurement process aimed at advancing the Bistrica pumped-storage hydropower plant, a significant infrastructure project in Serbia’s energy landscape. This development is indicative of the country’s commitment to enhancing its energy capabilities and reliability through strategic investments in renewable resources.

The procurement contract, estimated at around €5.2 million, focuses on creating a comprehensive suite of technical, planning, and regulatory documents necessary for the project’s construction phase. The objective is to secure all essential permits and strategic approvals promptly, minimizing potential delays once construction commences.

Central to this initiative is the enhancement of the Radoinja dam, alongside the formulation of preliminary and detailed designs required for obtaining construction approval. The scope encompasses extensive technical studies, notably geotechnical and seismic analyses, as well as advanced hydraulic modeling to ensure the integrity of key structures associated with the plant.

The project also integrates environmental and spatial planning elements, which include detailed strategies for managing areas designated for excavated material disposal. This work will be underpinned by complete technical documentation, necessary surveys, and urban planning frameworks that facilitate permitting processes.

Additional technical considerations will address slope stabilization, regulation of the Kratovska Riverbed, and measures to control erosion throughout the broader Bistrica watershed area. These efforts are crucial for ensuring both environmental sustainability and structural stability over the long term.

The tender further encompasses legal and property-related services such as land re-parcellation and expropriation planning, utilizing digital tools to enhance process efficiency. Environmental impact assessments will also be conducted for critical components of the project to guarantee compliance with both national and international regulations.

In addition to engineering tasks, the selected contractor will provide advisory support aimed at securing financing. This includes collaboration with international financial institutions like the Japan International Cooperation Agency (JICA), ensuring that all aspects of the project meet their technical and financial criteria.

Bidders interested in participating in this significant undertaking have until May 22 to submit their applications, marking a pivotal step in progressing toward the realization of the HPP Bistrica.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Djerdap 3 pumped-storage: Bechtel-Enka qualifies as Serbia prepares planning

Serbia has advanced work on the proposed Djerdap 3 pumped-storage hydropower project, with a Bechtel-Enka consortium qualifying for the next stage of government negotiations. At the same time, a Serbian engineering consortium is preparing the project’s planning framework. The...

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Serbian renewable projects face new contractual challenges on the Hungary export corridor

Export PPAs can expand market access for wind and solar projects, but the revenue ultimately reaching developers depends on delivery rights, trading costs and the share of output that qualifies for actual-emissions treatment. Serbian wind and solar developers targeting Hungarian...
Supported byVirtu Energy