Supported byClarion Energy
HomeNews Serbia EnergySerbia: 186,902 MWh...

Serbia: 186,902 MWh of electricity traded on SEEPEX in September

A total of 186,902 MWh of electricity was traded on the day-ahead market on the Serbian energy exchange SEEPEX in September, which is a 1.22 % increase compared to the previous month, with an average of 6,230.1 MWh/day.

Average daily base price on day-ahead market in September amounted to 63.67 euros/MWh, which is a 4.4 % increase compared to August, while average euro-peak price reached 70.77 euros/MWh (+ 8 %).

SEEPEX was officially launched on 17 February 2016, with traded volume 1,925 MW. It is jointly owned by Serbian electricity transmission system operator EMS and European Power Exchange (EPEX SPOT) with the idea to support the development of a competitive, transparent and reliable electricity market in Serbia and Southeastern Europe and make a significant impact on the increase of trading volumes of electricity in the region.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia, Montenegro power prices climb as Hungary-Germany spread narrows

Electricity prices in Serbia and Montenegro rose sharply for Tuesday delivery, moving against declines in Hungary and Romania as southeastern Europe’s reliance on imports increased despite stronger solar generation. The divergence highlights tighter local supply conditions in parts of...

Slovenia restarts Sostanj unit 5 to meet district heating demand

Slovenia’s Sostanj thermal power plant has temporarily restarted unit 5 as colder weather increases district heating demand. Unit 6 remains under maintenance while unit 5 is brought back into service. Heat demand has reached approximately 400 MWh a day. Unit...

E.ON Hungaria €625 million grid programme targets 2,323 MW connection capacity

E.ON is planning a €625 million expansion of its Hungarian grid. Separately, E.ON Hungaria is outlining a €625 million network investment programme aimed at adding 2,323 MW of connection capacity by 2030. The plan is intended to support additional...
Supported byVirtu Energy