Romania, Petromidia refinery could be closed for up to half a year

According to experts, Romanian biggest refinery Petromidia, operated by Rompetrol Rafinare which is owned by Kazakh KMGI Group, will remain closed for three to six months following the explosion at one of its units on 2 July.

The company said previously that it is collaborating with authorities to find the causes of the accident but provided no exact date for the resumption of the refinery’s operation. However, it promised to meet all the contractual obligations toward its customers by deliveries from either its own reserves or from the trading division of KMG International Group.

The statement from the company reads that the safe restart of the technological installations on the Petromidia platform depends both on the volume of repair works and verification of the machinery and equipment affected by the incident, and on the procurement of the equipment in the shortest possible time, in order to replace the affected ones.

On 2 July, KMGI Group said that its Petromidia Navodari refinery has stopped operation on 2 July
after a fire broke out at one of the installations. An incident took place on the platform of the Petromidia refinery, within the diesel oil refining installation (HPM). The incident resulted in death of three workers.

The explosion at the Petromidia refinery took place after the unit underwent a general overhaul between March and April 2020.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...

Romania becomes Southeast Europe’s battery-financing laboratory

Romania is moving beyond announcing battery projects and beginning to demonstrate how large-scale storage can actually be financed. August produced some of the clearest evidence yet. Econergy’s Părău 2 project secured a financing package of approximately €229 million from six banks and financial institutions. The...
Supported byVirtu Energy