In Romania total length of natural gas distribution network increased by 3 % in 2020, according to data published by the National Institute of Statistics (INS).

At the end of 2020, the total length of the pipelines within gas distribution system stood at 43,563.4 kilometers, of which 24,188.1 kilometers in municipalities and cities.

During the previous year, natural gas was distributed in 956 localities, of which 247 in municipalities and cities, while the length of distribution pipelines was extended by 1,276 kilometers.

At the same time, the volume of natural gas distributed at the end of 2020 was of 8.738 billion cubic meters, 289.6 million cubic meters less than the previous year. Of the total volume of natural gas distributed in 2020, 3.444 billion cubic meters or 39.4 % were for domestic consumption. Of the total volume of gas distributed, 87.5 % were distributed in urban areas.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...

Romania becomes Southeast Europe’s battery-financing laboratory

Romania is moving beyond announcing battery projects and beginning to demonstrate how large-scale storage can actually be financed. August produced some of the clearest evidence yet. Econergy’s Părău 2 project secured a financing package of approximately €229 million from six banks and financial institutions. The...
Supported byVirtu Energy