Romania: Hidroelectrica to complete long-delayed Rastolita hydropower plant by 2025

Romanian electricity producer Hidroelectrica is set to complete the long-awaited Rastolita hydropower plant in Mures County by the end of 2025, following government approval to clear over 30 hectares of forest to finalize construction.

Energy Minister Sebastian Burduja confirmed that the plant is 89% complete, with more than 144 million euros already invested in the project. Although construction began in 1989, the plant has faced numerous delays over the years.

Once finished, the Rastolita hydropower plant will be the first hydroelectric facility in recent Romanian history to be revived and completed after such a long hiatus. With an installed capacity of 35.2 MW, the plant is expected to produce 120 GWh of electricity annually, enough to power a small city. It will also play a significant role in supporting Romania’s transition to green energy.

The approval for deforestation was a key step in moving the project forward, as the final stages of construction involve modifying water flow and completing the reservoir. Despite some environmental concerns, the project is considered a strategic investment to enhance Romania’s renewable energy capacity and reduce its reliance on fossil fuels.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania extends 25% diesel excise reduction until Oct. 31

Romania will keep a 25% reduction in diesel excise duty until Oct. 31, extending temporary relief for transport operators and other businesses. The decision follows a period in which international fuel-market prices have risen faster than domestic pump prices....

R.Power completes 55-MW Lazuri solar plant in Romania; grid link by end-2026

Polish renewable-energy developer R.Power has finished construction of the 55-MW Lazuri solar plant in Romania’s Satu Mare county. Grid connection is expected before the end of 2026. The project is forecast to produce around 70 GWh annually, equivalent to...

Transelectrica to invest over €2.25bn in Romania grid upgrades through 2035

Romanian transmission system operator Transelectrica plans to invest more than €2.25 billion between 2026 and 2035 as part of a ten-year grid programme. The plan prioritises international interconnectors, completion of the domestic 400-kV transmission ring, and renewable integration. The...
Supported byVirtu Energy