Romania: Eurowind Energy expands wind portfolio with 138 MW project pipeline

Eurowind Energy Romania has announced three new onshore wind projects—Frumusita, Vector, and Pecineaga NorthEst—adding a combined capacity of 138 megawatts (MW) to its growing portfolio. The projects will utilize 23 Vestas V162-6.2 MW turbines from the EnVentus platform, strengthening the ongoing partnership between the Danish firms in the Romanian renewable energy sector.

Turbine delivery is scheduled for late 2026, with the projects expected to become operational in 2027. The Frumusita site in Galati County will include eleven turbines generating 66 MW. In Constanta County, Pecineaga NorthEst will deploy eight turbines with a total capacity of 48 MW, while the Vector project will consist of four turbines producing 24 MW.

Under the agreement, Vestas will supply, install, and maintain the turbines for 20 years through its Active Output Management 5000 service program. This long-term maintenance plan is designed to ensure consistent performance and reliability. The deal reinforces Vestas’s strong presence in Romania, where the company has installed over 1.5 gigawatts (GW) of wind capacity since 2009 and services more than 1.2 GW through its five service centers and a regional training hub employing over 550 professionals.

Romania’s favorable investment climate for renewables—bolstered by recent legal reforms, upcoming Contracts for Difference (CfD) auctions, and planned grid upgrades—continues to attract major industry players. Active in the Romanian market since 2011, Eurowind Energy currently operates four solar power plants in Halchiu, Magurele, Pufesti, and Teius. With approximately 7.5 GW of renewable energy projects under development, the company expects to increase its operational capacity to 124 MW by the end of 2025.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania sets rules for Black Sea wind with 3.1 GW potential

Romania has adopted initial regulations to open its offshore wind sector to investors, with three Black Sea areas offering about 3.1 GW of potential capacity. Transelectrica plans more than EUR 2.2 billion in transmission investment between 2026 and 2035 to support renewable generation and storage.

Rezolv secures up to EUR 367 million for 292.5 MW wind farm

Rezolv Energy secured financing of up to EUR 367 million for its Dunarea East wind farm in Romania, clearing the way for construction. The 292.5 MW project is scheduled to enter commercial operation in early 2029.

Romanian day-ahead power price hits EUR 239.32/MWh in October

Romania's day-ahead electricity price rose 35.87% from September and nearly doubled year on year, while traded volume remained below its October 2025 level. Transaction value climbed as higher prices outweighed limited volume growth.
Supported byVirtu Energy