Romania: EC Oltenia’s project to accelerate

The Ministry of Energy will set up a working group for coal-based electricity producer Energy Complex Oltenia, to identify solutions and collect data for the restructuring plan for the modernization of the company.

In 2022, the European Commission approved the restructuring plan of EC Oltenia worth 2.66 billion euros. The total value of the measures for the reorganization and transformation of EC Oltenia is close to 4 billion euros if the company’s contribution of some 1.24 billion euros is added to the sum.

More than 250 million euros have already been allocated, as support granted by the Romanian state in 2020, which is already included in the restructuring plan. About 711 million euros will be granted through the Modernization Fund, for the commissioning of 8 solar power plants with combined installed capacity of 725 MW, the refurbishment and modernization of a 10 MW micro hydropower plant and the commissioning of a natural gas-fired electricity generation capacity – a unit of 475 MW at TPP Turceni, and 850 MW unit at TPP Isalnita.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...

Romania becomes Southeast Europe’s battery-financing laboratory

Romania is moving beyond announcing battery projects and beginning to demonstrate how large-scale storage can actually be financed. August produced some of the clearest evidence yet. Econergy’s Părău 2 project secured a financing package of approximately €229 million from six banks and financial institutions. The...
Supported byVirtu Energy