Romania: E-Distributie Dobrogea received 9.6 million euros grant for distribution network upgrade

The Romanian Ministry of Energy and E-Distributie Dobrogea signed a non-refundable financing contract through the Modernization Fund, worth 9.6 million euros for the development, modernization and systematization of medium-voltage electrical installations related to the Navodari 110/20kV primary substation.

From the total value of the project, the maximum amount covered by the Modernization Fund is 80% of the eligible expenses, respectively 6.4 million euros. The project aims to modernize medium voltage networks, modernize substations and introduce the remote control system of substations, for the benefit of the residents of the Navodari area.

The validity of the contract ends at the end of the project sustainability monitoring period (five years from the date of commissioning of the investment). The estimated implementation period by E-Distributie Dobrogea is a maximum of 29 months.

Minister of Energy Sebastian Burduja said that some of the most important renewable energy production units are concentrated in Dobrogea, as well as NPP Cernavoda. The development of the distribution network is vital to the national energy system and the Ministry strongly supports the modernization of distribution networks.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

DPE 2026 in Rimini: A Hub for Energy Innovation and Collaboration

The DPE 2026 event held in Rimini, Italy, has emerged as a pivotal gathering for stakeholders in the energy distribution sector. This platform transcended the traditional trade fair format, facilitating a rich dialogue among utilities, technology providers, and enterprises...

Bulgaria: USTDA and ESO signed a deal to increase cross-border network capacity in the SEE region

The US Trade and Development Agency (USTDA) signed a grant agreement with Bulgarian electricity transmission operator ESO to advance new transmission infrastructure that will ease the integration of new renewable energy sources and increase ESO’s capacity to export electricity...

Romania: Six investors planning solar panels and energy storage plants compete for 200 million euro grants

Six bidders submitted projects to get grant financing under a EUR 200 million grant scheme operated by Romania and aimed at supporting the development of PV panels and power storage battery plants.  The scheme is financed by the National Resilience...
Supported byVirtu Energy