Romania: Delgaz Grid completes Onesti Centru transformer station, enhancing power supply for 31,000 customers

At the end of December 2024, Delgaz Grid successfully completed the construction and commissioning of the Onesti Centru transformer station, following an investment of over 4.6 million euros. This new station will benefit more than 31,000 customers in Onesti and surrounding areas.

The transformer station enhances service quality by improving electricity supply continuity, distribution efficiency, and increasing capacity for new consumers, prosumers, and renewable energy producers. Operating at a 110 kV voltage level, it provides greater reliability to the region’s electricity supply.

Key features of the project include the installation of 1.3 kilometers of 110 kV network with dual circuits, the construction of a new station with two power transformers, and advanced 20 kV energy distribution equipment. To further boost supply security, the Onesti Centru station is also connected to the Onesti 35 transformer station in the municipality. The station is equipped with advanced technologies that allow remote monitoring and control through integration into the SCADA system.

This development is part of a broader initiative co-financed by the Modernization Fund, which also includes upgrades to the Letea transformer station near Bacau. The total investment for the initiative exceeds 20.5 million euros, with around 13.7 million euros provided as non-reimbursable funding from the Modernization Fund and 6.8 million euros contributed by Delgaz Grid.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania’s power imports surge as renewable generation declines

Romania’s net electricity imports surged 82.08% to 135.72 GWh in the week ending 20 September, as weaker renewable and hydropower generation increased the country’s reliance on electricity from neighbouring markets. Wind and solar generation in Romania fell by 25.9%, while...

Cernavoda output loss expected to continue into October amid low Danube levels

Romania is expected to remain without output from the Cernavoda nuclear plant into October as low Danube levels continue to restrict cooling conditions. The prolonged outage is occurring during a tight regional power market, with increased reliance on cross-border...

Nala Renewables commissions 99.2 MW Green Breeze wind farm in Romania

Nala Renewables has commissioned the 99.2 MW Green Breeze wind farm in Romania, which has begun commercial operation. The project is located in Galați county and adds to the pipeline of corporate-backed wind generation in the country. Electricity from...
Supported byVirtu Energy