Supported byClarion Energy
HomeGasRomania: Completion of...

Romania: Completion of Iernut gas-fired power plant at risk due to contractor insolvency and delays

The completion of the 430 MW gas-fired power plant at Iernut, being built by the Spanish contractor Duro Felguera for Romgaz, is at risk due to the contractor’s insolvency issues and a 400 million euro fine related to its previous contract in Algeria. Originally expected to be finished in 2020, the plant is still not operational.

Duro Felguera has been seeking creditor protection since December 2024, aiming to begin talks for a restructuring plan. Romanian Minister of Energy, Sebastian Burduja, stated that if the Spanish company is unable to continue with the project, the government will intervene and directly pay the subcontractors involved.

Minister Burduja also mentioned that the TPP Iernut gas unit is 97% complete, which is a positive development. However, it still falls short of full completion. Although only 3% of the work remains, this small portion still presents significant challenges.

In November 2016, Romgaz entered into an agreement worth 268 million euros (excluding VAT) with a consortium of Duro Felguera and Romanian Romelectro for the construction of a new 430 MW gas-fired power plant at Iernut. The deadline for the project completion was set at 36 months from the effective date of the contract, which would begin within five working days from the date the NIP financing was approved. Romgaz took over the Iernut thermal power plant in 2013 from Bucharest-based thermal energy producer ELCEN, in exchange for canceling a 145 million euro debt.

In late 2020, Romgaz stated it would not grant an extension for the deadline of the gas-fired unit construction at the Iernut thermal power plant, as proposed by the project’s contractors—Duro Felguera and Romelectro. The agreed deadline for completion expired on 26 December 2020.

After prolonged negotiations, in April 2023, Romgaz signed a 70 million euro contract with Duro Felguera to complete the remaining works on the combined cycle gas turbine power plant at Iernut.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania extends 25% diesel excise reduction until Oct. 31

Romania will keep a 25% reduction in diesel excise duty until Oct. 31, extending temporary relief for transport operators and other businesses. The decision follows a period in which international fuel-market prices have risen faster than domestic pump prices....

R.Power completes 55-MW Lazuri solar plant in Romania; grid link by end-2026

Polish renewable-energy developer R.Power has finished construction of the 55-MW Lazuri solar plant in Romania’s Satu Mare county. Grid connection is expected before the end of 2026. The project is forecast to produce around 70 GWh annually, equivalent to...

Transelectrica to invest over €2.25bn in Romania grid upgrades through 2035

Romanian transmission system operator Transelectrica plans to invest more than €2.25 billion between 2026 and 2035 as part of a ten-year grid programme. The plan prioritises international interconnectors, completion of the domestic 400-kV transmission ring, and renewable integration. The...
Supported byVirtu Energy