Romania: BRHA pipeline may increase the gas transmission fees

The costs of transporting gas paid by end consumers might increase by 25-30 %, as the investment in the Bulgaria-Romania-Hungary-Austria (BRHA) gas pipeline must be amortized, and the pipeline risks remaining empty in the next period, said energy expert and former Minister of Energy Razvan Nicoleascu.

He reminded that the first phase of the BRHA pipeline has been completed. Transgaz has done a good job operationally in carrying out this project, without exceeding costs or major delays. However, the impact of this investment on the Romanian economy is not clear yet.

According to him, unfortunately Romania did not make enough efforts for the interconnections between Greece and Bulgaria to take place at the same time as the completion of the first phase of BRHA project, although the commitments have been assumed by everyone.

The European Commission has also not been uncompromising in its compliance with European commitments and legislation. Under these conditions, the risks of this pipeline remaining empty increase, especially since Romania will not have any significant production in the Black Sea in the next five years. In this undesirable case, the transport costs paid by end consumers could to increase by about 25-30 % because the amortization of BRHA cannot wait and will start soon, Nicolescu concluded.

The project, which connects Bulgaria, Romania, Hungary, and Austria, will increase Romania’s natural gas export and import capacity to Hungary to 1.75 billion cubic meters per year and the export capacity to Bulgaria to 1.5 billion cubic meters per year. The first stage’s cost amounted to 479 million euros, out of which 179 million euros came from the EU grant, while the rest was financed by natural gas transmission system operator Transgaz.

In June 2018, Transgaz has started the construction of the first phase of BRHA gas pipeline. Initial completion date of the first phase of BRHA gas pipeline was December 2019.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia targets early-2027 start for Romanian gas interconnector construction

Serbia expects construction of its gas interconnector with Romania to begin in early 2027, creating an import route intended to diversify supply and strengthen network resilience. Procurement for the Serbian section is expected to start shortly. Most technical and...

Lukoil appoints Eugene Maniakhine to oversee Petrotel refinery restructuring

Lukoil has appointed Eugene Maniakhine to oversee the restructuring of its Petrotel refinery in Romania. The facility entered insolvency proceedings in August 2026 after remaining offline since the previous year. The restructuring process is being handled under Romanian insolvency...

Romania targets Neptun Deep first gas in H1 2027 as execution advances

Romania has narrowed the Neptun Deep first-gas window to the first half of 2027, from a broader timetable previously associated with the €4 billion Black Sea development. The project is expected to bring about 8 bcm/year of production closer...
Supported byVirtu Energy