Romania, ANRE has granted regulatory approvals for the construction of new energy generation capacities of 97 MW

The National Energy Regulatory Authority (ANRE) has granted regulatory approvals for the construction of new energy generation capacities of 97 MW, which also includes the 46 MW cogeneration project of chemical company Chimcomplex.

Chimcomplex is planning to build a high-efficiency cogeneration power plant with installed capacity of 46.2 MW in Ramnicu Valcea.

In late 2021, the company bought some of the assets of bankrupt electricity and thermal energy producer CET Govora for 8.2 million euros and plans to build a combined cycle power plant at the site of the old plant. The assets bought from CET Govora include the old power plant with natural gas connection, with solid fuel warehouse and adjacent buildings. The capacity of the new plant is planned to cover electricity and thermal energy needs of Chimcomplex’ facility in Ramnicu Valcea and thermal energy needs of the city.

CET Govora is located in Ramnicu Valcea, where Chimcomplex has previously purchased the assets of bankrupt chemical complex Oltchim, and was used to provide district heating services to the municipality.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania extends 25% diesel excise reduction until Oct. 31

Romania will keep a 25% reduction in diesel excise duty until Oct. 31, extending temporary relief for transport operators and other businesses. The decision follows a period in which international fuel-market prices have risen faster than domestic pump prices....

R.Power completes 55-MW Lazuri solar plant in Romania; grid link by end-2026

Polish renewable-energy developer R.Power has finished construction of the 55-MW Lazuri solar plant in Romania’s Satu Mare county. Grid connection is expected before the end of 2026. The project is forecast to produce around 70 GWh annually, equivalent to...

Transelectrica to invest over €2.25bn in Romania grid upgrades through 2035

Romanian transmission system operator Transelectrica plans to invest more than €2.25 billion between 2026 and 2035 as part of a ten-year grid programme. The plan prioritises international interconnectors, completion of the domestic 400-kV transmission ring, and renewable integration. The...
Supported byVirtu Energy