Region: Slovenia- Hungary-Croatia electricity interconnection beginning of the construction works

The 80 kilometers long power line between Cirkovce near Ptuj and Pince on the border with Hungary will establish a link between the Hungarian and Slovenian national grids and consequently Croatia. The 150 million euros project has been in the making for almost two decades, mainly due to lengthy zoning procedures.

Slovenian Prime Minister Janez Jansa, his Hungarian counterpart Viktor Orban and Croatian Minister of Foreign Affairs Gordan Grlic Radman attended a ceremony in north eastern Slovenia, marking the start of the construction of a power line that will link the three countries.

PM Jansa noted that it took ten times as long to prepare the project as it would to build it. He said that Slovenia has terrible difficulties when it comes to the speed of development projects and zoning procedures, not so much with construction as with red tape, adding that the project should serve as a further encouragement that procedures should never again take that long. He said the power line was of exceptional importance not only for Slovenia but for a broader region.

Slovenian electricity transmission system operator ELES expects for the 2×400 kV power line to be linked internationally by the end of 2021 with the project to be fully completed with final details by the end of 2022.

In January 2019, EU member states have approved a grant in the amount of 48.2 million euros under the Connecting Europe Facility (CEF) to Slovenian electricity transmission system operator ELES for the construction of the first electricity interconnection between Slovenia and Hungary. The project implemented by ELES envisages the construction of the 80 kilometers long double-circuit 400kV overhead line Cirkovce-Pince and the new 400 kV Cirkovce substation, both in Slovenia. The new double 400 kV overhead line will be connected to one circuit of the existing double-circuit 400kV overhead line connecting Hungary and Croatia Heviz-Zerjavinec.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Paks nuclear output cuts linked to low wholesale prices amid Hungary’s solar growth

Hungary’s Paks nuclear plant has reduced generation again after electricity could not be sold economically during low-price hours. The latest curtailment reflects how rising solar output is affecting the country’s baseload market profile. Paks curtailment during low-price hours Paks cut...

Hungary granted temporary EU delay on Serbia gas capacity bundling rules

Hungary has received temporary approval from the European Commission to postpone full implementation of EU gas-capacity rules at its border with Serbia until the 2027/2028 gas year. The derogation relates to requirements that cross-border pipeline capacity be offered as...

Slovenia tests smart meters and EV charging as drivers of electricity flexibility

Slovenia is emerging as a key testing ground in Southeast Europe for how smart meters, dynamic network tariffs and automated electric-vehicle charging can transform ordinary electricity consumers into flexible power-market assets. Recent Slovenian pilots have demonstrated that EV charging can...
Supported byVirtu Energy