North Macedonia plans major Crni Drim refurbishment for HPP Globocica and Spilje

North Macedonia is preparing a new investment cycle in the Crni Drim hydropower system, focused on extensive refurbishment of HPP Globocica and HPP Spilje. The programme targets strengthening domestic generation using existing assets. Both plants have been in operation for more than half a century, with Globocica entering service in 1965 and Spilje in 1969.

Instead of replacing the facilities, the planned works are designed to extend their operating lives for decades. The scope is expected to include upgrades covering generators, rotors, bearings, block transformers and hydromechanical equipment. The stated aim is to improve reliability and efficiency while reducing operational risks linked to ageing plant.

Refurbishment scope and current asset performance

Globocica has already been uprated from an original 34.5 MW to 42.5 MW. Over its operating life, the plant has generated more than 10,500 GWh. Spilje has installed capacity of 84 MW.

Globocica’s output figures for 2026 are also part of the rationale for refurbishment planning. The plant produced 120 GWh in the first half of 2026, which was almost 19% above plan. That level was equivalent to around 80% of its full-year target within six months.

Potential expansion and hydro system modernisation

The Crni Drim system could also accommodate additional projects in the longer term. Options under consideration include Globocica 2, Spilje 2, and a floating solar plant on the Spilje reservoir. In parallel, North Macedonia plans to modernise systems that control water releases and water levels in Lake Ohrid and the Crni Drim.

This approach shifts the investment programme from conventional refurbishment toward broader optimisation of hydro operations across the system. The planned upgrades are intended to support continued use of dispatchable renewable generation already installed at Globocica and Spilje as part of efforts to reduce electricity-import exposure.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia targets 2027 construction start for €1.5 billion Čebren-Galište hydro project

North Macedonia is targeting a 2027 construction start for the long-planned Čebren and Galište hydropower projects, reviving a combined investment of up to €1.5 billion after years of unsuccessful concession attempts. Čebren is planned with a capacity of around 333...

North Macedonia eyes 2027 construction start for Čebren-Galište hydro complex

2027 target and combined investment North Macedonia is targeting a 2027 construction start for the long-planned Čebren and Galište hydropower projects. The government said the renewed push would revive a combined investment of up to €1.5 billion following repeated failed...

ESM launches third phase of €46 million upgrade for six North Macedonia hydropower plants

North Macedonia’s state-owned utility ESM has started the third phase of a programme worth roughly €46 million to modernise six large hydropower plants. The initiative is designed to upgrade existing generating assets rather than build new capacity. Capacity and...
Supported byVirtu Energy