Supported byClarion Energy
HomeElectricityMontenegro, TPP Pljevlja...

Montenegro, TPP Pljevlja to be offline for seven months in 2024

Director of Production department at thermal power plant Pljevlja Zoran Sljukic said that the plant will not require any downtime due to its environmental reconstruction during 2023, however, a 7-month long downtime is planned for 2024.

Sljukic also sad that the environmentally oriented reconstruction of TPP Pljevlja will be completed on 15 October 2024, after which a 5-month trial operation period will ensue.

Montenegrin state-owned power utility EPCG launched the environmentally oriented reconstruction of TPP Pljevlja this April, with the aim of increasing the plant’s operational life. The project’s value is 70 million euros and it should be completed in two and a half years.

In June 2020, EPCG signed a contract for the reconstruction of coal-based thermal power plant Pljevlja with a consortium led by Chinese Dongfang Electric Company (DEC). The selected consortium offer to perform the reconstruction for around 54.4 million euros including VAT. EPCG later decided to invest additional 15 million euros in the reconstruction.

Project implementation was scheduled to take place in the period 2019-2021, after which the operation of TPP Pljevlja will be enabled to continue for at least 20 years. Reconstruction will assure compliance with the requirements and adherence to the strictest environmental protection parameters as envisaged under the latest EU Decision 2017/1442.

Last April, the Energy Community Secretariat sent an Opening Letter to Montenegro to address its breach of the Large Combustion Plants Directive. In particular, the country’s sole thermal power plant Pljevlja, continues to operate despite the expiry of the limited lifetime derogation period of the plant.

Following a written declaration not to operate a plant for more than 20,000 hours after 1 January 2018, the limited lifetime derogation (also known as opt-out) was granted to selected installations by the Energy Community Ministerial Council. It is an implementation alternative to complying with the maximum emission limits set by the Large Combustion Plants Directive. Following the expiry of the 20,000 hours, the plants can only remain in operation if they meet the (stricter) standards of the Industrial Emissions Directive. This is not the case for TPP Pljevlja.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...
Supported byVirtu Energy