In the first nine months of 2020, According to EPCG Montenegrin state-owned power utility, TPP Pljevlja produced a total of 1.034 million MWh of electricity. EPCG said that its coal-fired thermal power plant Pljevlja exceeded the electricity production plan by 10 %.

In June, EPCG signed a contract for the reconstruction of coal-based thermal power plant Pljevlja with a consortium led by Chinese Dongfang Electric Company (DEC). The deadline for the completion of works is 39 months for the date of signing the contract. The selected consortium offer to perform the reconstruction for around 54.4 million euros including VAT. Project implementation is scheduled to take place in the period 2019-2021, after which the operation of TPP Pljevlja will be enabled to continue for at least 20 years. Reconstruction will assure compliance with the requirements and adherence to the strictest environmental protection parameters as envisaged under the latest EU Decision 2017/1442. The environmental reconstruction project includes the construction of the desulphurization system, denitrification system, enhancement of ESP operation as well as development of the waste water treatment system. Revitalization of Maljevac landfill valued at additional 20 million euros will take place concurrently. Close to 9 million euros was already spent on the project for revitalization of the landfill in the last year. The reclamation of the landfill will take place in stages between 2019 and 2023.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

World Bank-backed €50 million programme targets district heating in Pljevlja

Pljevlja transition programme and heating measures Montenegro is preparing an approximately €50 million World Bank-backed investment programme for Pljevlja. The effort targets district heating, cleaner household energy and efficiency measures as the country begins building infrastructure for an eventual transition...

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...