Montenegro’s sole coal-fired thermal power plant, Pljevlja, will shut down for at least seven months as it enters the final phase of its ecological reconstruction. The modernization project, led by state-owned power utility EPCG, officially begins on March 31 and aims to extend the plant’s lifespan while ensuring compliance with modern environmental standards.

EPCG confirmed that the €70 million reconstruction (excluding VAT) is progressing on schedule. More than 90% of the equipment, primarily sourced from China, has already been delivered and installed, with the remaining components expected by June 2025. During the seven-and-a-half-month production halt, EPCG will import electricity to cover the shortfall, ensuring no disruption for consumers. The company has already secured 788 GWh of electricity, valued at €81.7 million, and plans to optimize costs through operational trading.

The ecological upgrade will not affect electricity prices or impact the salaries and rights of TPP Pljevlja’s 182 employees. In parallel, work is progressing on the Pljevlja district heating project, a key initiative aimed at improving living conditions in the city.

EPCG emphasized its stable cooperation with Pljevlja coalmine, with both entities operating as an integrated energy complex to support Montenegro’s long-term energy security. All activities are proceeding as planned, with a strong focus on energy stability, environmental sustainability, and social responsibility.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Montenegro’s electricity exporters need stronger PPAs to secure Italian market revenues

The Adriatic interconnector gives Montenegro's renewable generators access to Italian buyers, but investment returns depend on carbon treatment, delivery profiles and the fallback provisions built into individual export agreements. Montenegro's electricity interconnection with Italy offers renewable energy investors access to...

Montenegro construction permit issued for 88 MW Korita wind farm near Bijelo Polje

Montenegro has issued a construction permit for the 88 MW Korita wind farm near Bijelo Polje, moving the project towards implementation. The authorisation was granted following completion of planning and environmental approval procedures. The permit was issued to local...
Supported byVirtu Energy