Montenegro, Late installation of transmission lines as part of a submarine cable project

On the Lastva – Čevo and Čevo – Pljevlja transmission lines, which are an integral part of the submarine cable between Montenegro and Italy, with a total length of 190 kilometers, 64 of the planned 680 poles have not been built.

According to the information adopted by the government in Podgorica on Thursday, the reason is unresolved property and legal relations and blockades of locals.

The realization of this project, which is at the top of the list of priority infrastructure projects, requires maximum interdepartmental cooperation at the government level as well as the support of all institutions involved in resolving disputed issues, the government document states.

One core of the submarine cable, with a capacity of 600 MW, was put into commercial use on December 28, 2019. The estimated capacity is almost twice as high and amounts to 1,000 MW.

That part of the project, along with the converter plant, worth 758 million euros, is the obligation of Italian Tema, and the transmission line and the Lastva substation, worth 113 million euros, should be financed by CGES.

Source: bankar.me

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Gvozd II wind expansion set for spring 2027 as EPCG complex reaches 76 MW

Montenegro is targeting spring 2027 for the commissioning of Gvozd II, as state utility EPCG expands its wind portfolio. The project is expected to bring the overall Gvozd complex to 76 MW. Construction activity is progressing on one of...

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...
Supported byVirtu Energy