Montenegro, Late installation of transmission lines as part of a submarine cable project

On the Lastva – Čevo and Čevo – Pljevlja transmission lines, which are an integral part of the submarine cable between Montenegro and Italy, with a total length of 190 kilometers, 64 of the planned 680 poles have not been built.

According to the information adopted by the government in Podgorica on Thursday, the reason is unresolved property and legal relations and blockades of locals.

The realization of this project, which is at the top of the list of priority infrastructure projects, requires maximum interdepartmental cooperation at the government level as well as the support of all institutions involved in resolving disputed issues, the government document states.

One core of the submarine cable, with a capacity of 600 MW, was put into commercial use on December 28, 2019. The estimated capacity is almost twice as high and amounts to 1,000 MW.

That part of the project, along with the converter plant, worth 758 million euros, is the obligation of Italian Tema, and the transmission line and the Lastva substation, worth 113 million euros, should be financed by CGES.

Source: bankar.me

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...
Supported byVirtu Energy