Montenegro, Gvozd wind project delayed due to pandemic

Montenegrin state-owned power utility EPCG said that the coronavirus pandemic is the main reason for the delay of its project for the construction of Gvozd wind farm because its consequences affected the global business environment and the energy sector, and all this was reflected in obtaining the necessary permits and negotiations on the financing of the project.

When EPCG initially announced this project, the expected start of construction was in 2021, and commissioning was expected 18 months after the start of the construction.

According to EPCG, the project will be financed through a loan from the European Bank for Reconstruction and Development (EBRD), with which the contract should be signed in December. The loan is worth 82 million euros.

The project is implemented through the project company Green Gvozd, which will be 100 % owned by EPCG. The company expects that it will obtain the construction permit within the next two months, which the connection permit from the transmission system operator CGES has already been obtained. The new deadline for the commissioning of Gvozd wind farm is 2024.

Wind farm Gvozd will have a total installed capacity of 55.4 MW and the expected annual electricity production of around 150 GWh.

In 2018, EPCG and Austrian Ivicom Holding signed a Memorandum of Understanding (MoU) on the construction of Gvozd wind farm. However, last year EPCG agreed to acquire 100 % of project company’s capital.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...
Supported byVirtu Energy