Montenegro: EPCG launches tender for 2.5 MW Slano solar power plant design

Montenegrin state-owned energy company EPCG has announced a tender for the preparation of project documentation for the construction of the Slano solar power plant, located on the Slano reservoir dam. The planned photovoltaic facility will have an installed capacity of 2.5 MW.

The tender, valued at 13,000 euros, requires bids to be submitted by August 13. The scope of work includes the complete design of the solar plant and its connection to the electrical grid, covering integration into the distribution network.

The main design package must contain the layout of the photovoltaic plant, substation designs, geodetic base maps, a connection study for integration into the 10 kV network, and a fire protection report. EPCG will separately provide the structural design for mounting the solar panels.

The total estimated cost of the Slano solar power plant project is 60 million euros. EPCG aims to complete at least five major projects within the next two years, with both the Slano and Krupac solar plants expected to be operational by the end of 2027.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...