Montenegrin company Deponija, the waste management company of Podgorica, plans to build a bioenergy plant and a waste-to-energy incinerator.

-The bioenergy plant project has already been launched and we will soon open a tender for drawing its feasibility study – Deponija head Aleksandar Bozovic said in a video published on the Facebook profile of Podgorica’s city administration.

The bioenergy plant will cost 1.7 million euros, while the incinerator could require an investment of up to 100 million euros.

The incinerator would be built on an area of 600 to 800 square metres. Depending on whether it will produce both electricity and heat, and whether it will cover the needs of Montenegro or Podrorica and its region alone, the project will cost between 35 million euros and 100 million euros, eKapija quoted Bozovic as saying.

Bozovic noted that the project already has a location study. The project will be financed by a credit that should be repaid in the first 5-6 years of the plant’s operations, Bozovic added without providing any financial details.

He noted that Deponija will receive 1 million euro from the city budget this year, for procurement of machinery and the launch of the new projects.

The incinerator could be built by the end of 2028.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Domestic industrial PPAs open new revenue opportunities for Serbian and Montenegrin renewables

Domestic industrial demand can support renewable investment and improve electricity cost predictability, but the carbon value of a power purchase agreement depends on the products being exported and the emissions rules governing them. Renewable developers in Serbia and Montenegro have...

Montenegro’s electricity exporters need stronger PPAs to secure Italian market revenues

The Adriatic interconnector gives Montenegro's renewable generators access to Italian buyers, but investment returns depend on carbon treatment, delivery profiles and the fallback provisions built into individual export agreements. Montenegro's electricity interconnection with Italy offers renewable energy investors access to...

Montenegro construction permit issued for 88 MW Korita wind farm near Bijelo Polje

Montenegro has issued a construction permit for the 88 MW Korita wind farm near Bijelo Polje, moving the project towards implementation. The authorisation was granted following completion of planning and environmental approval procedures. The permit was issued to local...
Supported byVirtu Energy