Slovenia’s proposed 1,100 MW Krško 2 nuclear unit would cost an average €132.92/MWh to produce power over its first 20 years and €13.5 billion to build at commissioning, according to calculations published by transmission system operator ELES. The cost estimate and the allocation of supporting system costs will inform whether the project remains competitive ahead of a referendum on construction.
ELES’s most likely average-cost figure is above an earlier estimate of at least €125/MWh. At about €133/MWh, projected output would be below this autumn’s spot-price levels and 2027 baseload forward prices of €169/MWh in Hungary and €145.50/MWh in Germany, although those forward contracts cover a period much earlier than Krško 2’s planned first 20 years of operation.
Slovenian day-ahead power averaged €233.68/MWh for 19 November. The comparison is between that market price and a projected average cost across the unit’s first two decades of operation.
Construction and system costs
ELES estimates construction costs at commissioning of €12.4–14.8 billion, with €13.5 billion the most likely figure. The calculation assumes annual inflation of 1% and a weighted average cost of capital of 4%; in 2024 prices, the baseline construction cost is about €10.25 billion before financing.
Earlier estimates put the cost at about €9.6 billion for a 1,000 MW unit and €15.4 billion for a 1,650 MW unit. Slovenia’s planned unit has a net capacity of 1,100 MW.
The system would need a 1,100 MW reserve for Krško 2, implying 500–600 MW of new gas-fired capacity at an estimated annual cost of about €31 million. A new high-voltage switchyard is estimated to cost €250 million, of which ELES would cover about €80 million.
Financing choices and project timetable
Key decisions remain open on the state’s role in financing the project, whether to offer a contract for difference with a price cap, and whether a strategic partner could take up to 50%. The financing model and allocation of reserve-capacity costs will determine whether the project remains competitive ahead of the referendum.
Slovenia’s government launched a national spatial plan for Krško 2 in February 2026. A referendum on whether to build the unit was expected at the end of 2027 or in early 2028.
The existing Krško plant is jointly owned by Slovenia’s GEN energija and Croatia’s HEP. Built as a joint project of the two former Yugoslav republics, it produced about 517 GWh in May, nearly half of Slovenia’s electricity output that month.