Greek power utility PPC has reached an agreement with construction and energy group GEK-TERNA for the purchase and transfer to Crete of a 147 MW gas-fired power plant, currently stationed in the Viotia area.

PPC, which has undertaken the task of ensuring energy sufficiency on Crete, plans to have the power plant transferred and reinstalled on the island in time for this coming summer when energy demand typically peaks.

PPC has included Heron I, the GEK-TERNA gas-fired power plant, in its package of solutions for energy sufficiency on Crete, both before and after the completion of a grid interconnection project to link Crete and Athens.

PPC and GEK-TERNA are expected to complete their agreement imminently so that the power plant’s transfer and reinstallation procedure can commence as soon as possible.

An agreement for PPC’s purchase of the power plant was reached by the two sides a while ago, but a remuneration formula for the power utility’s operation of the power plant on Crete, still not fully linked to the mainland grid, had remained pending.

At a meeting chaired by the energy ministry, a decision was reached to cover 75 percent of the power plant’s remuneration through the public service compensation (YKO) account, accumulating related surcharges added to all electricity bills. PPC will cover the other 25 percent.

The European Commission needs to approve the remuneration formula as it involves state aid.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

ADMIE secures equipment for €3.5bn of grid projects through 2029

Greek transmission operator ADMIE has secured equipment for projects worth about €3.5 billion, cutting procurement risk across more than half of its €6 billion investment programme through 2029. The move covers grid works scheduled within the operator’s multi-year plan....

Greece tests local flexibility markets as grid operators seek value from distributed power assets

Greece is testing a new electricity-market model that could create additional revenue for factories, EV fleets, commercial buildings and distributed energy assets while giving grid operators an alternative to some conventional network reinforcement. Projects involving transmission operator IPTO, distribution operator...

MVM begins foundations for 1 GW combined-cycle plant at Tiszaujvaros

Hungarian state-owned utility MVM has started foundation work on a new 1,000 MW combined-cycle gas-fired power plant at the former Tisza II site in Tiszaujvaros. The project is part of Hungary’s broader shift in generation needs as variable renewables...