Greece, Ministry of Energy is planning to set up deadlines for renewable energy projects

Greek Ministry of Energy is planning to set up deadlines for renewable energy projects which have obtained connection permits from the transmission system operator ADMIE but still have not progressed from the planning phase as a result of failure to submit contract applications in order to free up network capacity held by these stagnant projects.

In total, about 3.6 GW in RES projects have not progressed further from securing network connection permits. The Ministry estimates that some 1.5 GW of these projects will be removed, thus freeing up much needed network capacity.

RES projects that have received network connection permits up to 31 December 2020 will have a deadline of 30 June 2023 to submit their contract applications. Projects that received connection permits between 1 January and 31 December 2021 will have a deadline of 31 August 2023.

Sign up for updates & special reports

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy