Supported byClarion Energy
HomeSEE Energy NewsGreece: Komotini gas-fired...

Greece: Komotini gas-fired power plant secured 325 million euros loan

 

A joint venture of GEK-Terna and oil refiner Motor Oil, developing the 877 MW combined-cycle natural gas-fired power plant in Komotini in northeastern Greece, secured financing for the project for 325 million euros from Eurobank and Piraeus Bank. Development of the project is well over the halfway mark (about 60-65 % completed), to enter trial operation next year.

All of the main equipment to be installed at the plant has been received, while mechanical and electrical works are in progress, along with the development of a substation and connecting transmission lines.

A Siemens HL-class gas turbine, the first to be used in Greece, was installed at the plant earlier this year, with an energy efficiency of 64%.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary: The first green hydrogen plant starts trial operation

The first green hydrogen plant in Hungary was inaugurated on Monday at the Bükkábrány Energy Park in northeastern Hungary. At the inauguration ceremony, Energy Minister Csaba Lantos stressed that the plant not only serves the fight against climate change...

Serbia: When the first quantities of Azeri gas will arrive?

Serbia is still not receiving natural gas from Azerbaijan through the Bulgarian interconnector, which was put into trial operation on December 10th of last year. Deliveries from Azerbaijan will commence when there is a need for additional gas quantities, depending...

Serbia: Work on gas interconnection with Bulgaria completed

Serbian Mining and Energy Minister Dubravka Djedovic Handanovic announced on December 3 that all the work on the interconnector with Bulgaria has been completed and testing should begin this week on a "strategically important" interconnector to carry natural gas...
Supported byVirtu Energy