Greece: Interest in energy storage projects increased

In Greece investor interest in energy storage projects is already significant, although support mechanisms have not been established yet, according to data provided by Regulatory Authority for Energy (RAE).

Namely, RAE has received 123 applications for energy storage and pumped-storage projects since October 2019, representing a total of 12,229 MW. Of these applications, 110 are related to energy storage systems representing a total capacity of 9,102 MW.

So far, RAE has already issued production licenses for 38 energy storage projects with a total capacity of 3,582 MW.

The remaining 12 applications, representing 2,447 MW, are for pumped-storage units, not including a Terna Energy project in Amfilohia in northwestern Greece. So far, RAE has issued three licenses for pumped-storage facilities representing 807 MW.

According to initial estimates, subsidies provided for energy storage project would be enough to cover about 40 % of the project’s cost.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy